Home » PMI » PMP v.2 » Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
A. Applying calendars
B. Resource leveling
C. Resource planning
D. Resource conflict management
Correct Answer: B
Explanation/Reference:
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|