Which of the following best describes a work breakdown structure (WBS) that will be created?

The project team is involved in creating the work breakdown structure of the project. Which of the following best describes a work breakdown structure (WBS) that will be created?
A. The work should be decomposed to a realistic level of detail
B. If the work is not listed in the WBS, it is not in the project
C. The accumulation of the work in the WBS should be equal to the work of the project
D. All of the answers