Home » PMI » PMP v.2 » Written change requests should be required on______________
Written change requests should be required on______________
A. All projects, large and small
B. Only large projects
C. Projects with a formal configuration management system in place
D. Projects for which the cost of a change control system can be justified
Correct Answer: A
Explanation/Reference:
A system is needed for careful monitoring of changes made to the requirements. Use of written change requests encourages the individuals asking for changes to take responsibility for their requests and reduces frivolous requests that may adversely affect the project.
PMI®, PMBOK® Guide, 2013, 94-97 140