The key management skills required during the adjourning stage of team development include all but which one of the following?
A. Evaluating
B. Reviewing
C. Celebrating
D. Improving
Correct Answer: C
Explanation/Reference:
During the adjourning stage of team development, the emphasis is on tasks and relationships that promote closure and celebration. There is recognition and satisfaction as the theme is moving on and separation. Management skills involve evaluating, reviewing, and improving, while leadership qualities are celebrating and bringing closure.