When you review cost performance data on your project, different responses will be required depending on the degree of variance or control thresholds from the baseline. For example, a variance of 10 percent might not require immediate action, whereas a variance of 100 percent will require investigation. A description of how you plan to manage cost variances should be included in the______________
A. Cost management plan
B. Change management plan
C. Performance measurement plan
D. Variance management plan
Correct Answer: A
Explanation/Reference:
The management and control of costs focuses on variance thresholds. Certain variances are acceptable, and others, usually those falling outside a particular range, are unacceptable. They are typically expressed as percentage deviations from the baseline plan. The actions taken by the project manager for variances are described in the cost management plan.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|