What should the project manager do?

Product design is 60 percent complete when a team member notices that a required environmental parameter was updated. Incorporating this change will increase project costs.
What should the project manager do?
A. Request re-approval of the project scope via a signed contract.
B. Meet with the sponsor to discuss including the change in the project’s scope.
C. Initiate a change request with the change control board (CCB).
D. Inform the client about the change, and request additional funds.