What should the project manager do?

The project manager is about to finalize the project management plan when they discover a mistake. The team meets and identifies that the mistake will not have a high impact on the project.
What should the project manager do?
A. Wait for plan approval, and then submit a change request.
B. Inform management, and allow them to decide next steps.
C. Correct the mistake, and submit the plan for approval.
D. Escalate the situation to the project management office (PMO) for review.