As you work with your team to prepare your stakeholder management plan, you decided to develop a stakeholder engagement chart. You set it up so you could______________
A. Show the phase of your project of interest to identified stakeholders
B. Show gaps between current and desired levels of engagement
C. Determine which stakeholders you and your team felt were critical to project success but did not know about it
D. Determine when to involve key stakeholders in your project
Correct Answer: B
Explanation/Reference:
The stakeholder engagement assessment matrix is used as a tool and technique in plan stakeholder management. The purpose of the matrix is to show gaps between current and desired engagement levels to then ensure the plan provides these data.