Validate scope______________

Validate scope______________
A. Improves cost and schedule accuracy, particularly on projects using innovative techniques or technology
B. Is the last activity performed on a project before handoff to the customer
C. Documents the characteristics of the product or service that the project was undertaken to create
D. Differs from perform quality control in that validate scope is concerned with the acceptance-not the correctness-of the work results