What should the project manager do?

A project is nearing completion when the project manager learns that a change in market regulations may impact the project. What should the project manager do?
A. Check the stakeholder register.
B. Update the cost baseline.
C. Review the risk management plan.
D. Perform a cost-benefit analysis.