What should the project manager do before the next stakeholder’s project review meeting?

A project is six months into project execution when a key stakeholder leaves the company and another person from the same functional area is assigned to the project. The project manager updates all project documentation with this information.
What should the project manager do before the next stakeholder’s project review meeting?
A. Send all of the project documents to the new stakeholder.
B. Meet with the new stakeholder to introduce themselves and the team.
C. Bring the new stakeholder up to date on any unresolved problems in project.
D. Determine if the planned communications will meet the new stakeholder’s needs.