During the development of the scope management plan, a stakeholder requests the addition of pilot technology into the project scope to assist with product marketing. What should the project manager do?
A. Use the project reserve for the pilot technology.
B. Increase the project budget with the cost of the pilot technology.
C. Include the stakeholder in the scope planning meetings.
D. Review the scope baseline with the stakeholder.