All of the following statements are true except:

All of the following statements are true except:
A. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are outputs of integrated change control process
B. None of the choices are correct
C. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are inputs of integrated change control process
D. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are outputs of monitor and control project work process