Earned value analysis is a performance reporting tool/ technique. Which of the following best describes earned value (EV)?
A. Efficiency indicator to reflect schedule performance of project
B. Portion of approved cost estimate planned to be spent
C. Total of costs incurred in performing work activity
D. Efficiency indicator to reflect cost performance of project
E. Value of the work completed