Which of the following statements are true given the following data:

You are using three point estimating technique to estimate the duration of a schedule activity. Which of the following statements are true given the following data:
Pessimistic: 100 days
Optimistic: 40 days
Most likely: 65 days
Average: 68.33 days
Variance: 151.38
A. Not enough information is provided
B. The calculations were performed assuming a uniform distribution
C. The calculations were performed assuming a beta distribution
D. The calculations were performed assuming a potential distribution
E. The calculations were performed assuming a triangular distribution