Which activity or activities would you crash to save four months on the project?

You are presented the following schedule data regarding various project activities on the critical path:


You are told that the project has a negative float of 4 months. Which activity or activities would you crash to save four months on the project?
A. T, U, V
B. T, V
C. S, V
D. S,T, U
E. X

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.