You are in the process of making information available to project stakeholders in a timely manner. All of the following statements are true EXCEPT:

You are in the process of making information available to project stakeholders in a timely manner. All of the following statements are true EXCEPT:
A. You need the communications management plan as one off the process inputs
B. Communication skills, information distribution methods, and lessons learned processes are tools/ techniques you can use
C. Performance reports are one of the process outputs
D. You are in the project executing process group