What is the average duration estimate based on the following three point estimates?

You are the project manager for a construction company. Your firm has been contracted to complete the construction of a 10-story office building. This project will use three point estimates to calculate the estimates for activity duration. You have the following estimates for task A (creating the foundation). Assuming the triangular distribution what is the average duration estimate based on the following three point estimates? Pessimistic= 100 days
Optimistic= 40 days
Most likely=65 days
A. 66.66
B. 75
C. 70
D. 68.33
E. 65