Which of the following describes an input to the direct and manage project execution process that consists of documented, authorized directions required to bring expected future project performance into conformance with project plan?
A. Approved change requests
B. Implemented preventive actions
C. Implemented change requests
D. Approved preventive actions
E. Implemented corrective actions
F. Approved corrective actions