You are in the process of estimating the type and quantity of resources needed to complete individual schedule activities.

You are in the process of estimating the type and quantity of resources needed to complete individual schedule activities. All of the following are tools/ techniques you can use in this process EXCEPT:
A. Published estimated data, project management software
B. Expert judgment
C. Reserve analysis
D. Bottom-up estimating
E. Alternatives analysis