You are in the process of estimating the type and quantity of resources needed to complete individual schedule activities. All of the following are tools/ techniques you can use in this process EXCEPT:
A. Published estimated data, project management software
B. Expert judgment
C. Reserve analysis
D. Bottom-up estimating
E. Alternatives analysis