Which of the following is the LEAST appropriate tool/ technique to use in this process?

You are in process of monitoring the various project processes and their performance. Which of the following is the LEAST appropriate tool/ technique to use in this process?
Expert judgment
A. Earned value technique
B. Inspection
C. Project management methodology
D. Project management information systems