Which of the following statements regarding risk register is FALSE?
A. The risk register contains the results of qualitative risk analysis, quantitative risk analysis, and risk response planning
B. The risk register is a component of the project management plan
C. The lowest level of the RBS can be used as the risk register
D. The risk register provides information on risks regarding the probability of occurring, impact on objectives, proposed responses, owners and status
E. The risk register describes all identified risks, along with their description, category, and cause