All of the following statements are true regarding the critical path method EXCEPT:
The critical path method accounts for resource limitations
A. On a network path, the schedule flexibility is measured by the
B. difference between early and late dates
The critical path method performs a forward pass analysis and
C. backward pass analysis through the project schedule network paths.
Critical paths have either negative or zero total float
D. The critical path method calculates the theoretical early start and
E. finish dates for all schedule activities