Which document describes the business needs for this project, identifies key deliverables, and gives you authority to begin the project and start assigning resources?

You are the project manager for a large children’s toys manufacturer. You’ve been asked to manufacture the latest craze in "Dancing Widgets" for the upcoming Christmas season. You’ve been informed that the company needs at least one month lead time to distribute the Widgets in order to have the Widgets on retailers shelves for the Christmas season.
Hence, based on the current sales forecast you have been asked to deliver 100,000 units by august 1st at the latest. Which document describes the business needs for this project, identifies key deliverables, and gives you authority to begin the project and start assigning resources?
A. Ishikawa document
B. RFQ
C. WBS
D. RFP
E. None of the choices are correct

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.