Which of the following Project Management Knowledge Areas are you involved in?

You are currently the project manager for a software development project, developing a next generation data-mining tool. Your team is developing a new software product that will help customers better manage large volumes of data, especially for data reporting purposes. The CEO tells you that the project must be completed within 18 months. In order to meat theses strict deadlines you are currently in the process of estimating the duration of project plan activities, devising the project schedule, and monitoring and controlling deviations from the schedule. Which of the following Project Management Knowledge Areas are you involved in?
A. Project Integration Management
B. Project Time Management
C. Project Scope Management
D. Project Risk Management
E. Project Quality Management

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.