Which of the following statements are true?

You are the project manager at a construction company. Your company is in the process of developing a 500-unit apartment complex. Your company has subcontracted all the electrical wiring of the building to XYZ Electrical. The subcontractor’s work involved wiring the building for electrical power, as well as cable and Internet/Ethernet wiring. The subcontractor has just completed the work, and you are in process of inspecting his work.
However, you’ve just discovered that the subcontractor forgot to install the Cat-5 Ethernet/Internet cabling throughout the building. The subcontractor’s performance did not meeting the contractor requirements. Which of the following statements are true?
A. You are in the quality assurance process, and performed a quality audit of the contractor’s work
B. You are in the contract administration process, and performed a contract audit to verify the contractor’s work
C. You are in the contract administration process, and performed a variance analysis to verify the completeness of the contractor’s work
D. You are in the scope verification process, and performed a quality audit of the contractor’s work
E. You are in the performance reporting process, and performed a performance review of the contractor’s work

Download Printable PDF. VALID exam to help you PASS.