You are in the process of directing the performance of planned project activities and managing the various technical and organizational interfaces that exist within your project.

You are in the process of directing the performance of planned project activities and managing the various technical and organizational interfaces that exist within your project. All of the following are outputs of this process EXCEPT:
A. Final product, service or result
B. Implemented defect repair, work performance information
C. Requested changes, implemented change request
D. Deliverables
E. Implemented corrective actions, implemented preventive actions