You are project manager responsible for constructing a new sports arena for the upcoming Olympics. Construction begins on a project over a year ago.
The stakeholders of the project want a status report on the performance of the project to date. You’ve obtained the following measurements:
BAC=500, PV=500, AC=200, EV=300, CPI=1.5
You believe the type of variances that have occurred on the project to date are typical expect these variances to continue throughout the project. Based on the information above, what is the ETC for the project?
A. 200
B. 250
C. 133.33
D. 333.33
E. 400