You are in the process of estimating the number of work periods that will be needed to complete individual schedule activities. All of the following are valuable inputs to this process EXCEPT:
A. Risk register, activity cost estimates
B. Historical information, historical reference data
C. Project schedule network diagrams
D. Duration estimation databases
E. Activity resource requirements, resource calendar