Which of the following statements are true regarding cost and schedule variances?
A. The amount of variance of CV and SV values tend to increase as the project reaches completion
B. The amount of variance of CV and SV values remain the same as the project reaches completion
C. Schedule variance will ultimately equal to cost variance when project is completed
D. The amount of variance of CV and SV values tend to decrease as the project reaches completion