You are an information security project manager responsible for securing your cooperate network. Due to new regulations mandated by the Sarbanes-Oxley act your company’s upper management has tasked you with securing the company’s network infrastructure. Unfortunately, you lacked detailed knowledge regarding firewall and IPS-related technologies. You are relying on an outside security consulting firm to provide you with expert judgment regarding these technologies. You are trying to forecast how often you’ll require their expert judgment during your project. Expert judgment is a tool/ technique in all of the following processes EXCEPT:
A. Develop project charter
B. Develop preliminary project scope statement
C. Develop project management plan
D. Scope planning
E. Schedule development