Which of the following is LEAST likely to improve the accuracy of cost estimates produced through parametric cost estimating techniques?

Which of the following is LEAST likely to improve the accuracy of cost estimates produced through parametric cost estimating techniques?
A. When cost estimates for work packages, control accounts, and planning packages in the WBS are accurate and detailed.
B. When model is scalable
C. When parameters used in the model are quantifiable
D. When historical information used to develop the model is accurate