Which of the following is the primary constraint for this project?

You are the project manager fro the large children’s toy manufacturer. You have been asked to manufacture the latest craze in "Dancing Widgets" for upcoming Christmas season. You’ve been informed that the company needs at least one month lead time in order to have Widgets on retailer’s shelves for Christmas season. Hence, based on the current sales forecast you’ve been asked to deliver 100,000 units by November 1st at the least. Since the toys will be used by young children, the "Dancing Widgets" must be manufactured to meet very specific safety specifications.
Your company drives 90% of if its revenue from sales generated during the Christmas holiday season. As a result, you have been given a budget of $15 million dollars to complete this project. Which of the following is the primary constraint for this project?
A. Risks, since the widgets must be manufactured to meet very specific safety specifications
B. Time, since the delivery cannot be changed
C. Scope, since the forecast for 100,000 units may change once manufacturing begins.
D. Cost, since your budget has been fixed at $15 million

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.