The outputs from risk identification are usually contained in the document called a risk register. All of the following should be included in the risk register upon completion of the risk identification process EXCEPT:
A. List of potential responses
B. Rot causes of risks
C. Update risk categories
D. List of identified risks
E. Risk audits