Which of the following are you LEAST concerned with during this process?

The Monitor and Control Project Work process is performed to monitor project processes and performance. Which of the following are you LEAST concerned with during this process?
A. Maintaining the integrity of baselines by releasing only approved changes
B. Providing information to support status reporting
C. Analyzing and tracking project risks
D. Assessing performance to determine whether corrective actions are necessary
E. Comparing actual performance against project management plan