Which of the following statements are false regarding the cost change control system?

Which of the following statements are false regarding the cost change control system?
A. A cost change control system is integrated with integrated change control process
B. A cost change control system is included as part of the cost management plan
C. cost change control system defines the procedures by which the cost baseline can be changed
D. A cost change control system integrates project scope, cost and schedule to help the project management team assess the project performance
E. A cost change control system includes forms, documentation, and approval level required to for authorizing changes

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.