Home » PMI » PMI-001 » You are in the process of identifying and documenting the project roles and responsibilities and create staffing management plan. All of the following are tools/ techniques you can use EXCEPT:
You are in the process of identifying and documenting the project roles and responsibilities and create staffing management plan. All of the following are tools/ techniques you can use EXCEPT:
A. RBS, OBS
B. Organizational theory
C. RAM, RACI
D. General management skills
E. Networking
Correct Answer: D
Explanation/Reference: