Which of the following process did you just complete?

You are the project manager at a utility company. Due to the recent rise in the cost of petroleum, your organization is exploring cheaper, alternative forms of energy. You have just completed the project scope changes, requested changes, and updates to the project scope management plan. Which of the following process did you just complete?
A. Scope definition
B. Develop preliminary project scope statement
C. Scope planning
D. Scope verification
E. Develop project management plan

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.