Which of the following statements regarding WBS is false?

Which of the following statements regarding WBS is false? To identify the major deliverables of the project requires
A. analyzing the preliminary project scope statement The work package is the lowest level in the WBS
B. A WBS from a previous project can often be used as a template
C. for a new project
Different deliverables in the WBS can have different levels of
D. decomposition
The WBS is an outcome of the Create WBS process
E.