According to the PMI, which of the following best describes "phase exists"?
A. Reviews at the conclusion of a project phase to determine whether the project should continue
B. Assignment of additional resources to the project in an attempt to decrease the project timeline/ schedule
C. Process of exceeding the specified project requirements
D. Schedule compression by starting a new task/ phase prior to completing the current project tasks.