Which are the primary constraints for the project?

You are the project manager at information technology division of a large health care provider in the United States. Due to the new regulatory requirements enacted by HIPAA to ensure the privacy of confidential medical records, you have been assigned to audit all I.T. system to ensure compliance.
You need to ensure that all the data in database is encrypted to ensure confidentially. You need to ensure that all the users are properly authenticated and authorization to confidential information follows the least privilege principle.
The deadline to ensure the compliance with HIPAA regulations is within 120 days. Failing to complete the project in 120 days will result fine to your organization. You have been given a budget of $500,000 dollars. Due to the overall budget cuts this year, you have been told that the budget is $500,000 and cannot exceed from this. Which are the primary constraints for the project?
A. Scope
B. Schedule
C. Budget
D. Quality

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.