Which of the following project management process group can stakeholders be identified?

In which of the following project management process group can stakeholders be identified?
A. Planning, monitoring and controlling
B. Initiating, planning, executing, monitoring and control and closing
C. Initiating, planning and executing
D. Initiating only
E. Initiating and planning