Which of the following statements are true regarding the critical chain method?

Which of the following statements are true regarding the critical chain method?
A. In CCM, planned activities are scheduled to their latest possible planned and start and finish dates
B. The CCM uses, aggregate problem buffers in the project plan instead of individual activity/ task buffer
C. The critical chain describes longest path through a project schedule network after resource leveling
D. CCM factors in resource availability limitations when constructing the project schedule
E. The CCM focuses on managing the total float of network paths to ensure that project are delivered on schedule