You are in process of controlling changes to the project cost baseline. All of the following are outputs of this process EXCEPT:

You are in process of controlling changes to the project cost baseline. All of the following are outputs of this process EXCEPT:
A. WBS updates, WBS dictionary updates
B. Lessons learned, project management plan updates
C. Requested changes, recommended corrective actions
D. Cost estimates updates, cost baseline updates
E. Performance measurements, forecasted completion