Which of the following describes how the various risk management processes will be implemented, monitored, and controlled throughout the project and describes the criteria that are used to establish the risk threshold?
A. Workaround plans
B. Residual risks
C. Risk management plans
D. Checklists
E. Risk response plans
Correct Answer: C
Explanation/Reference: