Work performance information is an input to Cost Control process. It includes all of the following EXCEPT:
Estimates to complete schedule activities
A. Calculate CV, SV, CPI, and SPI values for WBS components
B. Percent complete of schedule activities
C. Deliverables that have been completed versus not yet completed
D. Cost authorized and incurred
E.