Which of the following statements regarding the project charter is FALSE?

Which of the following statements regarding the project charter is FALSE?
A. The project charter grants authority to the project manager to initiate the project
B. The project charter describes the business needs for the project, such as marketing demand, legal requirements, technological advances.
C. The project charter provides the project manager with functional power over personnel
D. The project charter should not be directly published by the project manager.