All of the statements are FALSE regarding Resource Calendars?

All of the statements are FALSE regarding Resource Calendars?
A. Project resource calendar identifies the quantity of resource available during each activity
B. Project resource calendar updates are an output of the Activity Resource Estimation process
C. Project Resource Calendar typically identifies resource-specific holidays and availability periods
D. Project resource calendar represent hierarchal structure of the identified resources by resource category and type