Which of the following are you LEAST concerned with during this process?

The monitor and control project work process is performed to monitor project processes and performance. Which of the following are you LEAST concerned with during this process?
A. Analyzing and tracking project risks
B. Reviewing and approving requested changes
C. Providing forecast to update current costs
D. Providing information to support status reporting
E. Assessing performance to determine whether corrective actions are necessary