You are in the process of estimating the type and quality of resources needed to complete individual schedule activities. All of the following are outputs of this process EXCEPT:
A. Resource calendar updates, requested change
B. Resource breakdown structure
C. Project schedule
D. Activity attributes update
E. Activity resource requirements